|
Back to Air Projects
Email concerning the attainment demonstration part of the SIP Suit. Hi
Kevin, Feb. 19,
2000 Here's an important SIP Suit issue that revolves around
how DEQ calculated ExEx and the actual ExEx. EPA's ExEx and DEQ's ExEx ExEx is defined in the Guidance, ('Guidance on use of
modeled results to demonstrate attainment of the ozone NAAQS'), page 12, as; ExEx = (Rank - 1)/(# of years
used for ranking) DEQ didn't use this ExEx but
instead calculated the number of times a certain set of meteorological
conditions is expected to occur in any year.
This is stated in SIP Appendix N on page 7-25, para. 3. "Using the results of the CART analysis, ExEx was calculated for each of
the primary episode days by dividing the number of days within each terminal
node by the number of years (9) for which the analysis was performed." This is a ridiculous attempt to make sure all ozone exceedance
days have an ExEx of 2 or less. This
approach can be carried to its illogical extreme by noting that 27 terminal
nodes were formulated in the CART analysis, only nine of which were associated
with ozone forming potential. So,
following the DEQ approach quoted above, one could take a terminal node
containing 18 days and no ozone exceedances, divide it by nine and find an ExEx
of less than 2 for days with no ozone exceedances???? DEQ doesn't give the complete CART results, but there
were undoubtedly many nodes with no associated ozone exceedances that have an
ExEx of less than 2. The Actual ExEx Fortunately, DEQ has provided enough information to
calculate the actual ExEx. First, the
rank must be found. For 19 August, 1993,
the data is given in Appendix N, page 7-31, para. 5. "In terms of ozone forming potential, as defined above, this node was
ranked thirteenth. Approximately 15
percent of the days within the CART dataset were estimated to have greater
ozone forming potential." The total number of days in the dataset is 9 years times
245 days per year. (See page 7-22,
para. six, which states that the analysis was based on data for each year from
"April through October"). Total number of days = (9 years) x (245 days/year)
= 2,205 days Of these 2,205 days, approximately 15% have greater ozone
forming potential than 19 August, 1993.
So, the rank for 19 August, 1993 is; Rank (19 August, 1993) = (2,205
days) x ( 0.15) = 330 The ExEx for 19 August can now be calculated from the
equation for ExEx as; ExEx (19 August) = (Rank -
1)/(# of years used for ranking) = (330 - 1)/9 = 25.4 This is the actual ExEx for 19 August, not the 1.9 that
DEQ used. Another important point that
demonstrates 19 August was not a severe day is that of the 17 days put into
this CART node only 19 August was an exceedance. This means that the meteorological
conditions associated with this node rarely create an ozone exceedance, i.e.
only once in nine years and only once in seventeen occurances. Also note, since this node was ranked thirteenth and only
nine nodes "were expected to
contribute to maximum ozone concentrations greater than 12.0 pphm",
DEQ recognizes that this node is not associated with meteorological conditions
that promote ozone formation. (See page 7-24, bottom paragraph). The same analysis can be done for the other two
days. For 16 August 1989 the CART
analysis found that 6% of the days have greater ozone forming potential. (See
page 7-29, para. 5) The Rank is then; Rank (16 August, 1989) =
(2,205 days) x (0.06) = 132.3 ExEx (16 August) = (132 -
1)/9 = 14.5 NOT A SEVERE DAY. Rank (25 May, 1990) = (2,205
days) x (0.002) = 4.4 ExEx (25 May) = (4-1)/9 = 0.33
A
SEVERE DAY. Conclusions Statistical Benchmark 1 was failed three ways. First, recognizing that only one of the
three primary days is categorized as serious (ExEx < 2.0), N is one and N-1
= (1-1) = 0. This means that there can
zero exceedances in any Defined Subregion.
Thus, Benchmark 1 is failed as many Defined Subregions have ozone
exceedances and one Subregion has two. Also, no exceedances are allowed on primary episode days
with ExEx > 2.0. The DEQ attainment
demonstration has two primary episode days with ExEx > 2.0 that have exceedances. Thus, Benchmark 1 fails twice more on this
issue. Statistical Benchmark 2 was failed three times as
well. Statistical Benchmark 3 didn't
have to be applied, but will fail in one of the three primary episode days. Gary |
|
|
 HOME |
 News |
 Projects |
 Contact Politicians |
 Join Lean | |